Project Updates

Project Update - Week ending 4th December 2015

4th December 2015

Phasing datesPhasing 7

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

CAPACITY - We are aware that some cabinets have reached capacity. BT have launched a new 'waiting list' facility. Please esure that you are put on this waiting list by your ISP.

 

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice


Cabinet 3 on the BISHOP NORTON exchange

Cabinet 79 on the BOSTON exchange

Cabinet 25 on the BOURNE exchange

Cabinet 6 on the BURGH exchange

Cabinet 7 on the BUCKMINSTER 7 exchange

Cabinet 602 on the FOSDYKE exchange

Cabinet 13 on the LONG SUTTON exchange

Cabinet 5 on the NORTH SOMERCOTES exchange

Cabinet 6 on the SAXILBY exchange

Cabinet 7 on the SAXILBY exchange

Cabinet 41 on the SKEGNESS exchange

Cabinet 42 on the SKEGNESS exchange

Cabinet 1 on the SWALLOW exchange

Cabinet 5 on the TORKSEY exchange



If you have any queries please contact us

 

Delayed cabinets

Please note that we can only provide updates on delayed cabinets.

Bainton 4 – new duct job with contractor. Estimated completion date 16/12

Bassingham 4 - Power connection on BT land. Property manager to agree. Estimated completion date 16/12

Billinghay 6 - KEIR Homes have signed the wayleave - To be programmed. Estimated completion date 16/12

Birchwood 63 - Estimated completion date 16/12

Burgh on Bain 3 - Programmed for 31/12

Burgh on Bain 4 - Still has outstanding wayleave issue for power

Chapel St Leonards 12 – Estimated completion date 16/12

Corby Glen 4 - With commissioners, service availability imminent

Cranwell 2 - Awaiting return of power wayleave; then 2 weeks notice required for clearance to site. Estimated completion early January

Cranwell 5 – Build complete; with commissioners

Fulbeck 606 - Under review due to engineering difficulties and associated excessive costs

Gosberton 5 – No response from Network Rail; chased again.

Grantham 16 - Estimated completion date early January due to difficulty in completing civils activity in advance of cab shift.

Grantham 21– New power date 15/12

Grantham 34 – Estimated completion date 9/12

Holbeach St Johns 1 - Expected January due to additional civils issues.

Huttoft 1 - Estimated completion date 23/12; 2 overlays to complete then cabling and jointing of spine

Huttoft 3 - Estimated completion date 23/12; 2 overlays to complete then cabling and jointing of spine

Kirton 5 - Expected January due to additional civils issues.

Kirton 8 - Civils delayed due to other utility in the area, Highways agreed new start date of 16/12; Estimated completion date 30/12

Lincoln 76 - Estimated completion date 9/12, chasing power date

Lincoln 132 – Estimated completion date 9/12, chasing power date

Lincoln 133 - New duct required to be laid - estimated completion date still 16/12

Long Sutton 4 - Estimated completion date 16/12

Metheringham 1 - Estimated completion date 9/12

Metheringham 6 - With commissioners, service availability imminent

Metherinham 14 - Estimated completion date 16/12

Old Leake 6 – Quality issue with civils work, will need a large amount of re-work - estimated completion date to January

Normanby By Spital 2 – Estimated completion date 9/12

North Somercotes 3 - Cabinet has been moved to facilitate new development. Estimated completion date 23/12

South Cockerington 2 - Estimated completion date 30/12; several overlays in progress, spine cabling and jointing to follow over Xmas period

South Cockerington 3 - Estimated completion date 30/12; several overlays in progress, spine cabling and jointing to follow over Xmas period

Spalding 50 – ECD 9/12. Joint visit with WPD to see if new Point Of Connection (POC) can be found so Nno need for deep excavation shuttering; work programme for 7/12

Spalding 16– Estimated completion date mid-January; additional blockages found

Spalding 26 – Build complete; with commissioners

Spalding 45 – Build complete; with commissioners

Spilsby 1 - Estimated completion date 16/12

Swaton 2 - With commissioners

Swaton 3 - Estimated completion date 9/12

Swinderby 1 - With commissioners, service availability imminent

Tetford EO (3) - Build complete; with scheme recorders

Withern 1- Land ownership change has caused dispute over wayleave for pole. WPD to seek alternatives.

 

November Progress

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide