Project Updates

Project Update - Week ending 4th March 2016

4th March 2016

Phasing datesphasing 8

 

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

CAPACITY - We are aware that some cabinets are at capacity, which will mean that you cannot order an upgrade at this point in time. BT is aware of this issue and is working to upgrade your cabinet. Unfortunately, BT do not provide information to us regarding when individual cabinets will be updated. They have launched a new 'waiting list' facility. Please ensure that you are put on this waiting list by your ISP.

 

Completed cabinet list

Cabinet 5 on the Bassingham exchange

Cabinet 2 on the Cranwell exchange

Cabinet 76 on the Lincoln exchange

Cabinet 2 on the Normanby by Spital exchange

Cabinet 5 on the Sibsey exchange

 

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

Delayed cabinets

Burgh on Bain 4 - Power connection re-booked for 16/03/16

Corby Glen 5 – Ready for service - products will be available from this cabinet within 2 weeks

Dowsby 5 - power booked for 11/04/16 but engineers are looking to bring this forwards; estimated completion date 31/03/16

Dowsby 602 - Estimated completion date 31/03/16

Fulbeck 606 - Estimated completion date 31/03/16

Gosberton 5 – Estimated completion date 31/03/16

Grantham 16 - Due to difficulty in completing civils activity in advance of cab shift. This has become more delayed - estimated completion 16/03/16

Grantham 34 – Power connection complete, expected to be live within two weeks

Greatford 8 - Ready for service - products will be available from this cabinet within 2 weeks

Holbeach St Johns 1 - Estimated completion date 31/03/16

Huttoft 1 - ecd moved to 23/3/16 due to conflicting civils work in vicinity

Huttoft 3 - ecd moved to 23/3/16 due to conflicting civils work in vicinity

Kirton 5 - Highways issues with civils work - expected completion date 23/03/16

Kirton 8 - Highways issues with civils work - expected completion date 16/03/16

Lincoln 50 - Cabinet stood; expected completion 16/03/16

Lincoln 132 – Estimated completion date 16/03/16

Metheringham 1 - Ready for service - products will be available from this cabinet within 2 weeks

Metheringham 3/2 (Nocton) - Estimated completion 31/03/16

Metherinham 14 - Ready for service - products will be available from this cabinet within 2 weeks

North Somercotes 3 - Ready for service - products will be available from this cabinet within 2 weeks

Owersby Moor E4 - On hold pending decision relating to high costs

Spalding 16 – Estimated completion 23/03/16 due to additional blockages

Withern 1 - Ready for service - products will be available from this cabinet within 2 weeks

 

progress feb

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide