Project Update - Week ending 4th September 2015

4th September 2015

Phasing datesPhasing 6-7

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

CAPACITY - We are aware that some cabinets have reached capacity. This is because BT build in the availability of a new service for a proportion of the businesses and residents when a cabinet is first enabled. This will increase dependant on demand. Please bear with us and capacity will be added as soon as possible

 

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

Cabinet 72 on the Birchwood exchange

Cabinet 2 on the East Kirkby exchange

Cabinet 3 on the Fulbeck exchange

Cabinet 2 on the Saltfleetby exchange

Cabinet 18 on the Sudbrooke Park exchange
 
 

Please note that we can only provide updates on delayed cabinets.

 

If you have any queries please contact us

 

Delayed cabinets

Ancaster 4 – Ready for service -  CRFS shortly

Bainton 4 – Position agreed by Highways Authority and Town planners have agreed to early start on this. Processes being expedited to make sure it gets to RFS ASAP

Bardney 6 – DELAYED – this cabinet will not be completed until quarter of October – December; new duct required over the bridge

Billingborough 1 - Cab site surveyed, location agreed with Highways Authority; with Contractors to stand and then we will joint, expected late this quarter / early next. 04/09/15 Blown fibre tube to joint box - with engineers to stand the cabinet

Billingborough 5 – Cab site surveyed, location agreed with Highways Authority; with Contractors to stand and then we will joint, expected late this quarter / early next 04/09/15 - dependant on Billingborough 1

Birchwood 63 - DELAYED – this cabinet will not be completed until quarter of October. BT cabling late August (half completed)

Birchwood 72 - RFS - internet services providers should be offering services in 1 weeks time

Buckminster 7 - Overlay works (on poles) required expected delivery in this quarter, before the end of September.

Chapel St Leonards 12 – Shifted in plan. Wayleave still outstanding with developer

Corby Glen 1 & 2 – Traffic management authorisation has caused these to be delayed A1+ will not let BT in to clear blockages & cable until the 7th September, should be available mid September

Cranwell 2 -  This cab is planned and job has been designated to the engineers to stand

Cranwell 5 – Second survey completed, awaiting formal survey return

Folkingham 1 – Fibre damaged by others. BT fibre jointers are working on this today. 04/09/15 Will be RFS next week - 2 weekks after this services can be ordered

Folkingham 3 – Fibre damaged by others. BT fibre jointers are working on this today 04/09/15 Will be RFS next week - 2 weekks after this services can be ordered

Gosberton 5 – Chasing Network Rail for a meeting to agree way forward

Grantham 16 - SHIFTED - Expected delivery between October and December

Grantham 21– Power wayleave still required, chasing with power company today 04/09/15

Grantham 34 – Chasing new date with power company for works under traffic management - chasing today 04/09/15

Holbeach St Johns 1 - DELAYED - All poles erected at the weekend, waiting remedail civils work likely to be RFS October - November due to size of the PON

Honington 1 – Power provision ongoing – long route which has meant delays. Waiting on WPD for a connection date. 04/09/15 Road crossing and power delivery due to be completed this week

Kirton 5 (amalgamated with 13) - Should be RFS early October as big copper job (De-load / Re-load with cab 13)

Knipton 1 & 3 – Outstanding civils - Expected to be clared by End of August 04/09/15 blockages should be cleared this week

Langrick 1– DELAY linked to new duct over bridge which requires various meeting with Bridge engineers and Contractors. 1KM of duct work to go over a deep dyke. In progress

Langrick 2 – power connection date will be 23/09/15

Lincoln 76 SHIFTED - Now expected late quarter 3, November - December 2015

Lincoln 132 SHIFTED – Now expected late quarter 3, November - December 2015

Lincoln 133 - Cab up and powered, needs copper and fibre, but new duct required which could cause further delay

Metheringham 6 - Cabinet stood in position. With planners to provide route utilising existing fibre

Old Leake 1, 3, 4, 5, 6 – DELAYED –  cabinets 1,3,4 and 5 should be ready for service at the end of September. Two weeks after this services can be ordered. Cab 6 will be delayed further as a new duct needs to be installed

Normanby By Spital 2 – High cost power - quote approved; Power wayleaves required

Sleaford 28 - Looking to use an existing fibre to expedite delivery. This cabinet should be completed by the end of this quarter, before the end of September

Spalding 50– New point of connection point found; with the engineering team to be programmed with Western power

Spalding 16 & 26– DELAYED - Completion will probably be in November, new duct required

Spalding 45 – DELAYED. New position agreed to avoid wayleave - now likely to be delivered between October and December

Spilsby 1- DELAYED - De-load / Re-load and road closure. Next quarter delivery

Swaton 2 & 3 Location for cabinet 3 has been rejected so planning works for this are ongoing - this has gone back for re-survey. Cabinet 2  is in job list to stand

Wickenby 2 – Chasing for power date

Withern 1 & 4 - Withern 1 waiting for engineering works which are due to be completed week ending 11/09/15; Withern 4 RFS

Witham on the Hill 1 & 2 New duct is required

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide