Project Updates

Project Update - Week Ending 5th December 2014

5th December 2014

Since the last update another 10 cabinet have been enabled which covers an additional 2078 premises.

 

Cabinet 2 on the BURGH exchange

Cabinet 3 on the BURGH exchange

Cabinet 117 on the LINCOLN exchange

Cabinet 131 on the LINCOLN exchange

Cabinet 1 on the MABLETHORPE exchange

Cabinet 3 on the MABLETHORPE exchange

Cabinet 2 on the RISEGATE exchange

Cabinet 4 on the SUTTERTON exchange

Cabinet 25 on the SKEGNESS exchange

Cabinet 5 on the WAINFLEET exchange

 

 

Cabinet progress update

Billinghay 1 There are unforeseen delays and duct blockages in relation to this cabinet – awaiting time frame from BT

Coningsby 4 - Another Point of Connection has been identified to avoid the asbestos but will need 40m of new duct to connect power. Job is ready for allocation

Cranwell 4 – Traffic management issues have caused unforeseen delays on this cabinet which will unfortunately not be completed before the end of December.

Grantham 81 – All the fibre tubing is installed – civils need to stand the cabinet which will likely happen after December.

Horncastle 3 - New location agreed with the Highways Agency, in the plan for deployment now

Moulton Chapel 1– Poles up and the Teams are on site. This cabinet will hopefully be ‘ready for service’ next week – two weeks after this it will be ‘customer ready for service’ and products can be brought from it.

Scampton 4 – ‘Ready for service,’ should be customer ready within the next two weeks.

Scampton 2 – This cab requires 386mtrs of new duct and is with the engineering team as a priority

South Rauceby 1 – Waiting for power source issue to be resolved to progress to completion

South Rauceby 2 – UPDATE RECEIVED 03/12/2014 - Highways have informed the OnLincolnshire Team that the road has now been adopted. Works should now progress.

Spalding 50 – Due to unforeseen delays this cabinet is not going to be stood until the middle of January

Spalford 1 – BT expect this to be 'ready for service' (RFS) next week – two weeks after this it will be ‘customer ready for service’ and products can be brought from it.

Sudbrooke 11Ready for service,’ should be customer ready within the next two weeks.

Wainfleet 4Ready for service,’ should be customer ready within the next two weeks.

 

Progress Thermometer December

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide