Project Update - Week ending 5th June 2015

5th June 2015

Phasing datesPhasing 5-6

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

 

CAPACITY - We are aware that some cabinets have reached capacity. This is because BT build in the availability of a new service for 20% of the businesses and residents when a cabinet is first enabled. This will increase dependant on demand. Please bear with us and capacity will be added as soon as possible

 

 

Completed cabinet list


Cabinet 2 on the CULVERTHORPE exchange

Cabinet 4 on the FENTON CLAYPOLE exchange

Cabinet 4 on the LONG BENNINGTON exchange

Cabinet 4 on the NAVENBY exchange

Cabinet 30 on the SLEAFORD exchange

Cabinet 48 on the SPALDING exchange

Cabinet 34 on the STAMFORD exchange

Cabinet 1 on the WOODHALL SPA exchange

 

 

Please note that we can only provide updates on delayed cabinets.


If you have any queries please contact us

 

 

Delayed cabinets

 

Ancaster 4 – Natural England now given Ok to start. Traffic management applied for to start works. 5.4Km of network to cable. 05/06/15 No Change – awaiting traffic management permission

 

Bainton 4 –Currently with planners, BT will push for early completion 05/06/15 BT are chasing planners for progression

 

Billingborough 5 – 1 Blockage left but this needs 3 way lights required (applied for). 05/06/15 Traffic lights booked for Friday 5th June

 

Billingborough 3 – 1 Blockage left but this needs 3 way lights required (applied for). 05/06/15 Traffic lights booked for Friday 5th June

 

Birchwood 72 - Cabinet stood in position, works are ongoing to get this ready for service 05/06/15 Cabinet is now powered and BT will be booked in copper and fibre works

 

Gosberton 5 – BT have agreed a method for spanning the bridge and are waiting for details of this work before it can be included in the engineers work stack. 05/06/15 No change

 

Grantham 21 – Power connection needs completing. Liaisons ongoing with the power company. 29/05/15 Traffic Management required for power road crossing, being organised. 05/06/15 No change

 

Grantham 34 – 500mts power which will delay enablement until July according to Western Power. 05/06/15 No change

 

Holbeach St Johns 1 - DELAYED – Will not be complete until July – September

 

Horncastle 3 – Duct work programmed/noticed this week, Power connection still required. 29/05/15 waiting for next possible date for power connection

 

Kirton 5 - work is with the engineers and is still pending. 05/06/15 No change

 

Lincoln 132 – Shifted in the plan - due for deployment July – September 2015 No change

 

Old Leake 3 – DELAYED – Will not be complete until July – September. Spine work is progressing but slowly working with traffic management clearing blockages

 

Old Leake 6 - DELAYED – Will not be complete until July – September. Spine work is progressing but slowly working with traffic management clearing blockages

 

Normanby By Spital 2 – Power outstanding but prioritised for delivery before the end of June. 05/06/15 Still waiting for power connection

 

Sibsey 1- Cabinet position has been agreed – this cabinet should be ready for service by the end of June, products will be available approximately 2 weeks after this. 05/06/15 No change

 

South Rauceby 1 – New power quote received and authorised, in the plan for power to be connected next week. 29/05/15 Deep excavation is required. Shuttering to be provided by contractor for this. 05/06/15 Reports that roadworks are not booked until the end of this month are correct – a road crossing is required for the electric feed which is going to require significant engineering. Significant delays of at least another month unfortunately

 

Spalding 50 –Still waiting details from Power Company due deep excavations on power. 29/05/15 Deep excavation is required. Shuttering to be provided by contractor for this. 05/06/15 No change

 

Sudbrooke Park 18 – Overlay is now complete, just needs the power to be certificated. 05/06/15 – Please accept our apologies for the ongoing delay on this cabinet. Unfortunately we were informed that all work was complete other than the power certification. This now seems to have been inaccurate and we now have to also complete both copper and fibre work at the cabinet. We will update as we progress'.


 

 

progress May 2015

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide