Project Update - Week Ending 6th February 2015

6th February 2015

Phasing 4-5

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

Since the last update another 3 cabinet have been enabled.

 

Cabinet 1 on the NEW LEAKE exchange

Cabinet 5 on the BILLINGHAY exchange

Cabinet 2 on the SOUTH RAUCEBY exchange

 

Cabinet progress update

Ancaster 2 – All traffic management is complete – this cabinet should be 'Ready for Service' shortly. Approximately two weeks after this, products can be ordered from it.

Ancaster 3 – All traffic management is complete – the cabinet now needs to be stood and for electrics to be provided.  

Ancaster 4 - All traffic management is complete – the cabinet now needs to be stood and for electrics to be provided.  

Billinghay 1 –There are still traffic management issues in relation to this cabinet and multiple blockages have been found in the underground ducting for all of the Billinghay cabinets. The teams are working hard to clear these.

Billinghay 6 – There are traffic management issues in relation to this cabinet and multiple blockages have been found in the underground ducting for all of the Billinghay cabinets. The teams are working hard to clear these.

Butterwick 3 – This cabinet should be 'Ready for Service' shortly. Approximately two weeks after this, products can be ordered from it.

Cranwell 4 – This cabinet should be 'Ready for Service' shortly. Approximately two weeks after this, products can be ordered from it.

Culverthorpe – Inspection with the Gas Board has been completed and works can now progress 

Donington 6 – The existing fibre needs to be taken down overnight; waiting for permission to do so.

Friskney cabs x 4 – Friskney 2 & 3 should be 'Ready for Service' this week. Approximately two weeks after this, products can be ordered from it

Grantham 81 – still planned for cabinet to be stood in February

Horncastle 3 – Cabinet will be stood in mid-February

Normanby by Spital EO Lines - Cabling and power connection works are still ongoing

South Rauceby 1 –Network Rail have given BT permission to proceed with works. BT are going to prioritise South Rauceby 1 to ensure it is completed as soon as possible. South Rauceby 2 is CRFS (Customer Ready For Service) Please call your ISPs as you can now order a product from this cabinet.

Spalding 50 –Still due for deployment in March

Spalding 56 – Cabinet due to be put in position by the end of the month and enabled by the end of March

Spalford 1 – Should be 'Ready for Service' this week. Approximately two weeks after this, products can be ordered from it

Welton EO lines –Welton 9 is still ongoing – blockages are causing delays

Withern Cabs x 2 Delayed – There are issues on the spine to Withern and there is currently no estimated completion date available.

Progress Thermometer 05.02.14

 

 

 

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide