Project Updates

Project Update - Week ending 6th February 2016

8th February 2016

Phasing datesphasing 8

 

 

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

CAPACITY - We are aware that some cabinets have reached capacity. BT have launched a new 'waiting list' facility. Please esure that you are put on this waiting list by your ISP.

 

Completed cabinet list

No cabinets have been enabled this week

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

Delayed cabinet

Bassingham 4 – now powered, but requires power certification, CT chased for update

Billinghay 6 – Products should be available from this cabinet within two weeks – ‘ready for service’ cabinet physically complete

Burgh on Bain 4 - Power connection booked 29/01/16

Cranwell 2 - Cabinet is now powered. Estimated completion 10/02/16

Corby Glen 5 – Estimated completion end of February / beginning of March

Fulbeck 606 - Will be added back in programme following review.

Gosberton 5 – Contact has been made with National Rail. Requires road closure once plans are agreed

Grantham 16 - Due to difficulty in completing civils activity in advance of cab shift. This has become more delayed - estimated completion mid-February

Grantham 34 – Shifted - estimated mid-February

Greatford 5 - delayed as duct damaged during roadworks. Expected delivery for February

Holbeach St Johns 1 - Expected mid-February due to additional civils issues.

Huttoft 1 - Estimated completion date shifted – delayed to 17/02/16

Huttoft 3 - Estimated completion date shifted - delayed to 17/02/16

Kirton 5 - Highways issues with civils work - expected completion date TBC.

Kirton 8 - Highways issues with civils work - expected completion date TBC.

Lincoln 50 - Lane closure agreed with Lincs Highways Authority. Expected completion 28/02/16

Lincoln 76 - Estimated completion date 25/02/16

Lincoln 132 – Estimated completion date 25/02/16

Lincoln 133 - Products should be available from this cabinet within two weeks – ‘ready for service’ cabinet physically complete

Louth 38 – estimated completion late March

Metheringham 1 - Traffic management re-booked estimated completion date shifted 24/02/16

Metherinham 14 - PLEASE NOTE - there is a computer records issue here currently being resolved by an expert but there may be slight additional delay, 29/01/16 BT are still working on resolving this

Moulton 7 - Awaiting power connection, road closure required; estimated completion date 23/03/16

North Somercotes 3 - Estimated completion date 19/2

Old Leake 6 – Products should be available from this cabinet within two weeks – ‘ready for service’ cabinet physically complete

Owersby Moor E4 - duct issue under railway. Awaiting quote from contractor.

Normanby By Spital 2 – Issue with power pole, power connection booked 18/02/16

Roxton 7 - Delay due to power wayleave

Spalding 16 – Estimated completion 12/02/16 due to additional blockages

Spilsby 1 - Date issue here, BT are chasing this to find out when products will be available.

Withern 1 - No change – alternative solution to power being sought

 

January progress

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide