Project Update - Week Ending 6th March 2015

6th March 2015

Phasing datesPhasing 4-5

 

 

 

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

Since the last update another 5 cabinets have been enabled.

 

Cabinet 62 on the BOSTON exchange

Cabinet 3 on the BUTTERWICK exchange

Cabinet 6 on the DONINGTON exchange

Cabinet 38 on the GAINSBOROUGH exchange

Cabinet 13 on the HUMBERSTON exchange

 

 

 

Cabinet progress updates

 

Please note that we can only provide updates on delayed cabinets.

The team are finding that the majority of cabinets are being enabled towards the very end of a phase, so the next influx will be towards the end of March for Phase 4 cabinets.

If you have any queries please contact us

 

 

ISSUES

South Rauceby 2 & product sign up- BT believe this is a data catch up issue. BT has masses of code to update systems; the data upload is a monthly activity so hopefully the latest upload will make a difference. It's been passed to the BT Sales team to double check.

 

DELAYED

Billingborough 3 No further update unfortunately - delays are still being caused due to blockages in the ducts for the Culverthorpe cabinets.

Billinghay 1 –Traffic management to clear two blockages started on Wednesday 4th March. Once the blockages are cleared, BT will be able to feed in the fibre. BT expects this to be RFS by the end of the month. Two weeks after this products can be ordered from it.

Culverthorpe – No further update unfortunately - Traffic management is required to clear blockages along the route - works still ongoing.

Donington 6 – This cabinet is 'Ready for Service.' In approximately one week products can be ordered from the cabinet.

Holbeach St Johns 1 - Shifted in the plan. Now to be enabled July - September 2015

Horncastle 3 –Awaiting update

Lincoln 132 – Shifted in the plan - due for deployment July – September 2015

Spalding 50 –Due new cabinet to be stood in week commencing the 9th March ready for delivery by the end of the quarter, as scheduled.

Welton 9 – works on this are still ongoing. Aiming to be ready for delivery by the end of March

Progress Thermometer 05.02.14

 

 

 

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide