Project Updates

Project Update - Week ending 6th November 2015

6th November 2015

Phasing datesPhasing 7

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

CAPACITY - We are aware that some cabinets have reached capacity. BT have launched a new 'waiting list' facility. Please esure that you are put on this waiting list by your ISP.

Swinderby 5 & 6 - capacity should be added by the 11th November - please be ready to order your new service

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

There are no cabinets to report as complete this week.

 

 

If you have any queries please contact us

 

Delayed cabinets

Please note that we can only provide updates on delayed cabinets.

Bainton 4 – Cabinet stood and powered and jointing works to progress

Bardney 6 – Ready for service - products should be available in the coming weeks

Bassingham 4 - only requires power now, booked in for 10/11/15

Billinghay 6 - will be enabled this quarter, before the end of December

Birchwood 63- Estimated completion mid-December

Buckminster 7 - Estimated completion mid-November

Burgh on Bain 3 & 4 - Power wayleaves required. Ongoing discussions with landowner 30/10/5 no change

Chapel St Leonards 12 – Wayleave in place - to be programmed into work schedule

Cranwell 2 - Estimated completion mid-December

Cranwell 5 – Estimated for completion before the end of November

Fulbeck 606 - aim to provide update next week.

Gosberton 5 – Estimated for completion before the end of December

Grantham 16 - SHIFTED - Expected delivery between October and December. Civils work commenced 09/10/2015

Grantham 21– Estimated completion now early December

Grantham 34 – Estimated completion mid-December

Holbeach St Johns 1 - Estimated completion mid-December

Huttoft 1 - Estimated completion mid-December. Requires new duct for power connection

Huttoft 3 - Fibre needs to be provided - estimated at the beginning of November 30/10/15 - DELAY Estimate completion mid-December

Kirton 5 DELAY - estimated completion before the end of December

Kirton 8 - estimated completion before the end of December

Lincoln 76 SHIFTED - Now expected late quarter 3, November - December 2015

Lincoln 132 SHIFTED – Now expected late quarter 3, November - December 2015

Lincoln 133 - New duct to be installed to allow provision of Copper and Fibre. Work commencing late October 30/10/15 Estimate completion by the end of December

Long Sutton 4 - DSLAM needs moving - estimated completion mid-December

Metheringham 1 - Power connection date has had to be changed as a new source has been identified which required a road crossing - estimated for 12/11/15 Ready for service estimated late November

Metheringham 6 - Power connection date has been changed - now estimated for 12/11/15 FURTHER DELAY - estimated completion for the end of November

Metherinham 14 - Digby - Estimated for completion for the end of November

Old Leake 6 – Civils issues are ongoing - expected to be ready for service mid-December

Normanby By Spital 2 – DELAY - cabinet failed commissioning tests. With Huawei to resolve. Huawei at site 26/10/15 Estimate completion mid-December

North Somercotes 3 - Cabinet has been moved to facilitate new development

South Cockerington 2 - overlay works in progress (over poles) Estimated completion mid-December

South Cockerington 3 - Estimated completion mid-December

Spalding 50– Estimated completion mid-December

Spalding 16– Estimated completion mid-December

Spalding 26– Estimated completion by the end of November

Spalding 45 – DELAYED. New position agreed to avoid wayleave - now likely to be delivered between October and December

Spilsby 1- Estimated for completion before the end of November

Spilsby 4 - Just needs power and certification. Working with power company to get dates for this. Estimated for delivery 14/11/15 late November

Swaton 2 & 3 - Highways Authority originally rejected location for Swaton 3; we now have agreement on location. Estimated cab stand date 12/11/15 Swaton 3 expected completion before the end of November

Swinderby 1 - Planner has released fibres BT can use - expected ready for service mid-December (probably before this in reality)

Tetford EO (3) Ready for service - products should be available in approx 2 weeks

Torksey 3 - Failed power certification, power company are going back to retest.

Wickenby 2 – DELAY - Estimated completion mid-December

Withern 1- Estimated completion late December

Witham on the Hill 2 - Estimated completion late November

 

November Progress

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide