No new cabinets have been enabled this week but BT are still pursuing their THP goals and are completing important infrastructure works.

 

An update is provided below for the current outstanding cabinets. If you would like any information about a cabinet that not listed below, please do not hesitate to contact us at onlincolnshire@lincolnshire.gov.uk

 

Progress Updates

Birchwood 44 – Imminently ready for service (RFS) – will be able to take orders 2 weeks after this.

Coningsby 3 – Imminently ready for service (RFS) – will be able to take orders 2 weeks after this

Coningsby 4 An asbestos duct has been identified leading to this cabinet which needs to be removed by a specialist team. The work has been allocated and this duct will be removed as soon as possible.

Coningsby 6 – Imminently ready for service (RFS) – will be able to take orders 2 weeks after this.

Grantham 81- Fibre is near the area. Now waiting for the cabinet to be stood so this can be connected by the relevant teams

Horncastle 3 - Cabinet being stood in position week commencing 12/11/2014

Moulton Chapel 1– infrastructure work is ongoing.

Ruskington 3 – Imminently ready for service (RFS) – will be able to take orders 2 weeks after this.

Scampton 4 - This is due for completion on the 16th November. The cabinet will then be ready for service (RFS) – will be able to take orders 2 weeks after this.

South Rauceby 1 – due to be completed before the end of December

South Rauceby 2 – Land adoption in progress - Public Notice in place for one month. This is now in place and it is due to end in mid-November.

Spalding 50 – Due to unforeseen delays this cabinet is not going to be stood until the end of December

Spalford 1 – Cabinet placement and infrastructure has been re-planned. The altered workload has been allocated to the engineering teams.

Sudbrooke 11 - Imminently ready for service (RFS) – will be able to take orders 2 weeks after this.

Wickenby 1 - Imminently ready for service (RFS) – will be able to take orders 2 weeks after this.

Wainfleet  4 – Cabinet is stood – fibre is in place but waiting for spine work from Skegness.

 

Over the coming weeks work will be carried out in or around the following areas providing Fibre Spine cables (From one Telephone Exchange to another):

Q2 Skegness - Burgh, Wainfleet, Spilsby, Boston, Butterwick, Stow, Withern, Honington, Ingoldsby, Sutton On Sea, Swaby

In addition, we will be continuing to work on various cabinets in other areas of the county.

Please note that this is not an exhaustive list and is for indication only.

Progress Thermometer 17.10.2014

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provider.