Project Update - Week ending 8th January 2016

8th January 2016

Phasing datesPhasing 7

 

We hope that you have a lovely Christmas and a very happy new year! Thank you for your ongoing support of the onlincolnshire programme

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

CAPACITY - We are aware that some cabinets have reached capacity. BT have launched a new 'waiting list' facility. Please esure that you are put on this waiting list by your ISP.

 

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

Cabinet 21 on the GRANTHAM exchange

Cabinet 63 on the BIRCHWOOD exchange


If you have any queries please contact us

 

Delayed cabinets

Bainton 4 – Ready for service - orders can be made within two weeks

Bassingham 4 - Wayleave agreed, power connection booked for 27/1

Billinghay 6 - Estimated completion date 21/1

Burgh on Bain 3 - Just needs power - booked in for this 18/01

Burgh on Bain 4 - Power connection booked 29/01

Cranwell 2 - Awaiting return of power wayleave; then 2 weeks notice required for clearance to site. Estimated completion 10/2

Fulbeck 606 - Will be added back in programme following review.

Gosberton 5 – No response from Network Rail; chased again.

Grantham 16 - Estimated completion date 27/1 due to difficulty in completing civils activity in advance of cab shift.

Grantham 34 – Estimated completion date 20/1

Greatford 5 - delayed as duct damaged during roadworks. Expected delivery for February

Holbeach St Johns 1 - Expected mid-February due to additional civils issues.

Huttoft 1 - Estimated completion date 3/2

Huttoft 3 - Estimated completion date 3/2

Kirton 5 - Expected 27/1 due to additional civils issues.

Kirton 8 - Civils delayed due to other utility in the area, Highways agreed new start date of 16/12; Estimated completion date 27/1

Lincoln 50 - Lane closure agreed with Lincs HA. Expected completion 28/2

Lincoln 76 - Estimated completion date 25/2

Lincoln 132 – Estimated completion date 25/2

Lincoln 133 - Estimated completion date 2/3

Metheringham 1 - Traffic management booked, estimated completion date 3/2

Metherinham 14 - with commissioners, service availability expected within 2 weeks

Old Leake 6 – Quality issue with civils work, will need a large amount of re-work - estimated completion 27/1

Normanby By Spital 2 – Issue with power pole, power connection booked 18/2

North Somercotes 3 - Estimated completion date 19/2

South Cockerington 2 - with commissioners, service availability expected within 2 weeks

Spalding 16 – Estimated completion 12/2 due to additional blockages

Spilsby 1 -  Ready for service - orders can be made within two weeks

Withern 1 - Land ownership change has caused dispute over wayleave for pole. WPD to seek alternatives. No change - alternatives being sought


November Progress

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide