Project Updates

Project Update - Week ending 8th May 2015

8th May 2015

Phasing datesPhasing 5-6

 

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

 

 

Completed cabinet list

 

No cabinets have been enabled this week

 

 

 

Please note that we can only provide updates on delayed cabinets.


If you have any queries please contact us

 

Delayed cabinets

Billingborough 5 – includes the amalgamated cabinet 1 lines. There is one blockage to clear in Billingborough now and estimations are that all works should be completed by the end of May

Billingborough 3 – just waiting for the fibre to be provided to the cabinet, however, there are multiple blockages in ducting (which required traffic management) in the ducts coming from Folkingham which, along with others, feed the Billingborough Cabinets. There is one blockage to clear in Billingborough now and estimations are that all works should be completed by the end of May

Billinghay 1 – DELAY – 844m of fibre remaining to lay. Traffic management to deal with this this began 30th April.

Birchwood 72- Cabinet not yet stood. Provisional date for this is the 27th May

Culverthorpe – BT expect Culverthorpe 1 to be ‘ready for service’ next week – approximately 2 weeks after this products can be ordered from it. Culverthorpe 2 will be stood in position as a priority. Due to be completed before the end of June.

Gosberton 5 –BT have agreed a method for spanning the bridge and are waiting for details of this work before it can be included in the engineers work stack

Grantham 21 – Power connection needs completing. Liaisons ongoing with the power company.

Grantham 34 – Cabinet not yet stood. Provisional date for this is the 28th May

Holbeach St Johns 1 - DELAYED – Will not be complete until July – September.

Horncastle 3 – 8m of new duct needs to be installed; this is a priority for their contractors

Kirton 5 - work is with the engineers and is still pending

Lincoln 132 – Shifted in the plan - due for deployment July – September 2015

Old Leake 3 – DELAYED – Will not be complete until July – September. Major traffic management required

Old Leake 6 - DELAYED – Will not be complete until July – September. Major traffic management required

Navenby 4 – DELAYED - Engineering complete and with Internet Providers but now waiting for systems to be updated. Products availalble soon.

Normanby By Spital 2 – Power outstanding but prioritised for delivery before the end of June.

Sibsey 1- Delivery of completed cabinet expected in June.

South Rauceby 1 – an alternative plan is now in place to source power – awaiting timescales for this.

Spalding 50 –BT is on track with current deployment. UPDATE - Spalding cabinet 50 is stood but it requires deep excavation & technical works for the power connection. The electric company are to schedule in joint site visit next week. UPDATE - The visit went ahead and the power company are looking for an alternate power source.

Sudbrooke Park 18 – Shifted slightly in the plan - due to be completed before June 2015

Sutterton 3 – The road crossing for the power has been completed, power connection is booked for 08/05/2015. This should be 'Ready for Service' next week. Two weeks after this products can be purchased from it.

 

April 2015

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide