Project Update - Week Ending 9th January 2015

9th January 2015

 

 Phasing 4-5

 

Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here


 

Since the last update another 14 cabinet have been enabled.

 

Cabinet 1 on the BAUMBER exchange

Cabinet 17 on the BOSTON exchange

Cabinet 4 on the CONINGSBY exchange

Cabinet 12 on the HORNCASTLE exchange

Cabinet 10 on the KIRTON exchange

Cabinet 1 on the MAREHAM LE FEN exchange

Cabinet 29 on the SKEGNESS exchange

Cabinet 5 on the SPILSBY exchange

Cabinet 2 on the SUTTERTON exchange

Cabinet 2 on the SUTTON ON SEA exchange

Cabinet 4 on the SUTTON ON SEA exchange

Cabinet 6 on the SUTTON ON SEA exchange

Cabinet 3 on the WAINFLEET exchange

Cabinet 4 on the WAINFLEET exchange



Cabinet progress update


Ancaster 2 – Traffic Management is booked in for 10 nights from the 11th January to deal with the blockages on the spine ducting coming out of Sleaford exchange.

Ancaster 3 – Traffic Management is booked in for 10 nights from the 11th January to deal with the blockages on the spine ducting coming out of Sleaford exchange.

Ancaster 4 - Traffic Management is booked in for 10 nights from the 11th January to deal with the blockages on the spine ducting coming out of Sleaford exchange.


Billinghay 1 – Just waiting for the fibres to be joined at the cabinet – this work has been designated to engineers


Billinghay 6 – This cabinet is situated on private land and BT are scheduling a meeting with the property developer to agree a position for the new cabinet. This isn’t expected to be ready until mid February.


Butterwick 3 –The existing copper infrastructure needs some reorganising inside the cabinet. They are hoping to start work on this on the 12th January


Cranwell 4 – Traffic management issues are still ongoing.


Culverthorpe 1 & 2 – Blockages are still being progressed through


Friskney cabs x 4 – Blockages coming out of Skegness are being dealt with.


Grantham 81 – This is still on track for cabinet positioning to take place in January


Horncastle 3 – Cabinet needs to be stood in position and power needs to be provided which is set to take place on January 15th, subject to unforeseen delays.


Heckington 1 –21M overlay completed, will be cabled & jointed on the 12th January

Normanby by Spital EO Lines - Delays in place due to collaped duct - this needs to be replaced by engineers before the works are completed.


Scampton 2 – This cabinet is 'ready for service'–  in approximately two weeks it will be ‘customer ready for service’ and products can be brought from it.


South Rauceby 1 –BT are hoping for this cabinet to be 'ready for service' by the end of January


South Rauceby 2 – Road is now confirmed as adopted and work is ongoing. This cabinet is expected to be ready in January, although there have been some further delays


Spalford 1 – New ducting is required –booked in with the contractors this Saturday, jointing Monday 12th Jan.


Withern Cabs x 2 – Estimated completion date of 7th February 2015.

 progress thermometer 090115

 

 

 

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide