Project Update - Week ending 9th October 2015

9th October 2015

Phasing datesPhasing 7

 Our newsletter now provides fortnightly project updates including completed cabinet lists - please sign up here

 

CAPACITY - We are aware that some cabinets have reached capacity. This is because BT build in the availability of a new service for a proportion of the businesses and residents when a cabinet is first enabled. This will increase dependent upon demand. We are pushing BT to clear these issues as a matter of urgency, conscious that some cabinets are unavailable for an unacceptably long period. Please bear with us and additional capacity will be added as soon as possible

 

Completed cabinet list

Can you get it? Check using these PDF instructions if you'd like to know before contacting the Internet Service Provider of your choice

 

Cabinet  1 on the  BASSINGHAM exchange

Cabinet  1 on the KNIPTON exchange

Cabinet  12 on the METHERINGHAM exchange

Cabinet  4 on the NORMANBY BY SPITAL exchange

Cabinet  7 on the ROXTON exchange

Cabinet 1 on the SOUTH COCKERINGTON exchange

Cabinet 4 on the SOUTH COCKERINGTON exchange

Cabinet 3 on the WICKENBY exchange (feeds Newtoft)

 

If you have any queries please contact us

 

Delayed cabinets

Please note that we can only provide updates on delayed cabinets.

 

Ancaster 6 - RFS. EO cabinet so may take longer than normal (i.e. 2 weeks) for products to be available

Bainton 4 – All surveys back, due for standing 2nd Oct.

Bardney 6 – DELAYED – this cabinet will not be completed until quarter of October – December; new duct required over the bridge

Billinghay 6 - will be enabled next quarter, before the end of December

Billingborough 1 - Ready for service. In approx two weeks products can be ordered from this cabinet.

Billingborough 5 – Will be made live to Internet Service Providers once Billingborough 1 has gone live

Birchwood 63 - DELAYED – this cabinet will not be completed until quarter of October.  BT cabling late August (half completed)

Buckminster 7 - Overlay works (on poles) required expected delivery in this quarter, before the end of September. DELAY - Delays in cabinet build due to agreement of Sunday working/road closure. Likely completion mid-October

Burgh-on-Bain 3/4 - UPDATE Waiting power and light. Expected completion 30th Nov

Chapel St Leonards 12 – No change but we are meeting with the Developer (Keir Homes) next week

Cranwell 2 -  This cab is planned and job has been designated to the engineers to stand. Cabinet stand and completion is forecast for next quarter

Cranwell 5 – Second survey completed, awaiting formal survey return. Delivery forecast for next quarter

Folkingham 3 – Ready for Service - products will be available to order from this cabinet in approx 2 weeks

Gosberton 5 – Overlay required over the bridge, Next quarter delivery

Grantham 16 - SHIFTED - Expected delivery between October and December

Grantham 21– There is currently a dispute over cabinet positioning

Grantham 34 – Chasing new date with power company for works under traffic management - chasing today 04/09/15

Holbeach St Johns 1 - DELAYED - All poles erected at the weekend, waiting remedial civils work likely to be RFS October - November due to size of the PON

Huttoft 1 - works are currently in progress

Huttoft 3 - Copper works are complete, need to re-plan fibre provision

Kirton 5 (amalgamated with 13) - Should be RFS early October as big copper job (De-load / Re-load with cab 13)

Knipton 1 - Ready for service - products should be available to order in approx 1 week.

Langrick 1– DELAY linked to new duct over bridge which requires various meeting with Bridge engineers and Contractors. 1KM of duct work to go over a deep dyke. In progress

Lincoln 76 SHIFTED - Now expected late quarter 3, November - December 2015

Lincoln 132 SHIFTED – Now expected late quarter 3, November - December 2015

Lincoln 133 - Cab up and powered, needs copper and fibre, but new duct required which could cause further delay

Metheringham 1 Due to be supplied with power 12th October - (Digby, Roughton?)

Metheringham 6 - Cabinet stood in position. With planners to provide route utilising existing fibre 11/09/15 Due to be supplied with power 12th October

Metheringham 12 - only needs fibre providing and the fibre jointers are delaing with this now

Old Leake 6 –  Civils issues are ongoing

Normanby By Spital 2 – Ready for service - services can be ordered from this cabinet in approx. 2 weeks.

Sleaford 28 - Will be RFS 2nd October

South Cockerington 1, 2 & 4 - 1 and 4 are ready for service - products can be ordered from these in approx 2 weeks. 2 has overlay works in progress (over poles)

Spalding 50– New point of connection point found; with the engineering team to be programmed with Western power

Spalding 16 & 26– DELAYED - Completion will probably be in November, new duct required

Spalding 45 – DELAYED. New position agreed to avoid wayleave - now likely to be delivered between October and December

Spilsby 1- DELAYED - De-load / Re-load and road closure. Next quarter delivery

Spilsby 4  - Just needs power and certification. Working with power company to get dates for this.

Swaton 2 & 3 - Next quarter delivery. HA originally rejected location for Swaton 3; we now have agreement on location.

Swinderby 1 - Cable recovery teams working to try to save the need to put in 3km of new duct. UPDATE 14/10/15 - cable recovery team have been working on this for two weeks

Wickenby 2 – Road crossing for power. 22/10/15

Withern 1- UPDATE 14/10/15 Cab is stood, overlay of copper and fibre programmed for this week. Looking to get power connection 22nd October

Witham on the Hill. Cabinet 1 is ready for service - products should be available to order in approx 2 weeks. Witham 2 still waiting for cabinet to be stood.

 

October process

 

To check if enhanced services are available at your address you can use the following link Wholesale Availability Checker, if enhanced services are available you will notice FTTC listed in the "Featured Products" column of the table. Those wishing to upgrade should contact their Internet Service Provide